WCS Preparation guide
Installation Requirements
- The Warmboard Comfort System (WCS) must be installed by a licensed general contractor, heating professional, or plumber. Failure to use a properly licensed installer, failure to use the required parts and components, and/or any deviation from these installation guidelines may void related product warranties.
- In order for WCS to operate correctly, tubing loops
must be installed according to our documentation.
Do not revise tubing loops or zones without first consulting Warmboard Inc. - WCS uses proprietary, plug-and-play controls including thermostats, manifold controllers, and a Smart Reset Controller. These items cannot be exchanged with alternative products.
- Do not adjust any equipment settings without consulting Warmboard. Changes made through the SRC or the boiler’s LCD screen can impact system performance and operation.
- The use of a combustion analyzer is required to calibrate safe and effective combustion in natural gas and propane boilers. Failure to do so could result in injury or death
![]()
- Follow all instructions and complete the Lochinvar and SpacePak registration cards.
- Read these highlights before proceeding to save time, money and hassle.
- Warmboard products are required to be installed and managed by experienced and licensed trade professionals pursuant to current local laws. Failure to use proper installers will void any product warranty.
- Review this guide and the supplied working drawings (including the floor plan dimensions)
- Do not revise tubing loops or zones without consulting Warmboard. Field changes will impact operation.
WARNING
Breathing Hazard – Carbon Monoxide Gas
Breathing carbon monoxide can cause brain damage or death. Always read and understand the instruction manuals.
- Do not operate heater if flood damaged.
- Install a vent system in accordance with local codes and manufacturers’ instruction.
- Do not place chemical vapor emitting products near the unit.
- Per NFPA 720, carbon monoxide detectors should be installed outside each sleeping area.
- Never operate the heater unless it is vented to the outdoors.
- Analyze the entire vent system to make sure condensate will not become trapped in a section of vent pipe, thereby reducing the open cross sectional area of the vent.
WCS Preparation
WCS is a unique offering that changes many aspects of a project which installers may be accustomed to.
Control components, water temperatures, and network devices are all pre-configured and plug-and-play. Simply follow the instructions in this guide and the system will work.
Essential Documents
A general contractor is required to manage the job site and trade professionals involved. It is important to keep the Warmboard-supplied documents on site at all times as multiple contractors may need to reference them regularly. These documents include:
- 24″ x 36″ WCS Plan Set (provided with each shipment in the Panel Installation Kit)
- Equipment manuals (included with equipment)
The content below shows the most common sequencing of a WCS project.
This guide is organized to follow these steps and ensure a successful installation of the Warmboard Comfort System.
Warmboard-S Sequencing
- Pour foundation and roll joists.
- Install Warmboard-S.
- Frame walls.
- Repeat previous steps for remaining levels.
- Sheath exterior.
- Head out manifold cabinet locations.
- Install tubing, install manifolds, and loop labels.
- Install supply and return distribution lines for manifolds.
- Rough-in electrical (e.g. boiler, thermostat, manifold controller…).
- Rough-in mechanical (see equipment manuals).
- Insulate and drywall.
- Complete system electrical and plumbing.
- Install Warmsource and other mechanical equipment.
- Fill the system, commission Warmsource, and set flows.
- Complete finish carpentry, finish floors, and paint.
- Install thermostats and manifold controllers.
- Connect system to local internet.
Warmboard-R Sequencing
- Ensure the existing subfloor or slab is level, flat, and 100% dried in.
- Install Warmboard-R.
- Head out manifold cabinet locations.
- Install tubing, install manifolds, and loop labels.
- Install supply and return distribution lines for manifolds.
- Rough-in electrical (e.g. boiler, thermostat, manifold controller…).
- Rough-in mechanical (see equipment manuals).
- Insulate and drywall.
- Complete system electrical and plumbing.
- Install Warmsource and other mechanical equipment.
- Fill the system, commission Warmsource, and set flows.
- Complete finish carpentry, finish floors, and paint.
- Install thermostats and manifold controllers.
- Connect system to local internet.
Next up, follow the Radiant heat panel install guide.
Go back to the WCS install guide.